VIDEO: Update on A592 Windermere gas mains upgrade

[W]ork is due to begin on the final two phases to replace gas mains under the A592, beside Lake Windermere.

Cadent are moving their gas pipes to assist United Utilities in its larger project to install a new wastewater pipe.

Cadent was given the window between 8 May and 31 October to complete our work, which we are doing in four phases.

Moving our gas pipes by Lake Windermere from Cadent on Vimeo.

A spokesman for Cadent said: “I’m pleased to say that we are on track and making good progress.

“The final two sections (phases 3 and 4) are both due to start on Monday.

“Phase 3 is at Ferry Nab and phase 4 is on a stretch of the A592 just south of Storrs Hotel.

“We will work hard to ensure access is available to all homes and businesses, at all times.

“Our work is in one lane of the two-lane carriageway, so we are controlling traffic flow with temporary traffic lights. We monitor traffic all the time and to date, the waiting times have rarely been higher than 45 seconds.

“We’ve worked hard to accommodate events (stopping work to assist a marathon and a cycle race earlier in the summer, for example) and to keep traffic flowing while we carry out the work.

“We’ve gone door-to-door to explain the works and residents / businesses can also contact our customer team on 0161 703 1000 / 1010.”

Cadent (formerly National Grid Gas Distribution) is the UK’s biggest gas distribution network. We maintain and repair 131,000km of pipes across our networks, to keep energy flowing to 11m homes and businesses.

Cadent A5 info leaflet Windermere phases 3 and 4

Related posts

Work of lake wardens and rangers in the spotlight

Cumbria Crack

Offers in excess of £3m sought for Miller Howe

Cumbria Crack

Heart of the Lakes becomes first cottage agency to support vital fundraising charity

Cumbria Crack

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More